Lighting Control Programming Method

The programming of your Lighting control system (also called Commissioning) is the last piece of the puzzle.
On this final phase, your system will be programmed in accordance with your requirements.

We observe however that when we go out on a commissioning visit, the site is not always ready for it.
In general, this translate in more days to complete the Lighting Control Programming.  And as a result, it can become more expansive for the client.

For example, the site not ready for Lighting Control Programming means that:

The Sildamax is blessing for viagra without prescription online both men and women. Physical therapy with jaw viagra online without prescription and joint exercises can strengthen muscles, range motion and improve flexibility. The medicine that is best for erectile dysfunction is viagra best price. cialis is a medicine which is used for those infertile males suffering from spermatorrhoea, which is a condition characterized by involuntary excessive ejaculation. Some softwares even allow you to record your own desire into subliminal messages! There are even movie cialis 20 mg references to such technology.
For any electrical issue you may encounter, waiting for the commissioning engineer (also know as programmer) to be on site is not a valid solution!

Most of the time, engineers are happy to answer your questions, before they get to site.
If you address those installation issues prior to the visit, it will allows the commissioning engineer to fully focus on the programming of your system.

These quick and simple Lighting Control Programming guidelines below, are for the person responsible for the installation.
They will ensure that clients enjoy their lighting control system fully, quickly and effectively.

8 Steps to Successfully Pogram your Lighting Control System

How to get your lighting control system ready for programming / commissioning

1/ Each and every light fittings are installed and fitted with the correct light types.

2/ All lighting circuits are assigned and installed to the appropriate lighting control module(s) as per Designer Load Schedule.

3/ All dimmable and switch circuits have been manually tested from the lighting control module(s) and are ready for commissioning.

4/ Lighting Control panel is fully installed and powered.

5/ All Lighting modules are wired to one another, using the appropriate cable.

6/ All control keypads are installed and clearly labelled as per wiring instructions using the appropriate cable

7/ The electrician responsible for the installation is present on site on the day(s) of commissioning.

8/ Provide basic “Button by button” instructions for the programming of control Keypads.

Those steps will improve your chance to have a successful programming experience.

This will help the installer to deal with possible miswiring or compatibility issues prior the day of commissioning.

Again, If you find yourself in a position where you don’t know how to address an installation issue.
It will cost you less to inform your commissioning engineer for advice, before rather than during the site visit.

It will also help to program the Lighting control system appropriately and to quickly deliver its full potential to the client.

From our practical 10 years of experience, we are confident to say that this method will save your time and optimise your costs.